A renovation checklist for an occupied flat

The sequence matters more than the schedule, because the wrong order means doing work twice.

A renovation checklist for an occupied flat

Order everything by how wet and how dusty it is. Civil work and plumbing first, then electrical chasing, then waterproofing and tiling, then ceiling, then joinery, then painting, then flooring protection off and soft furnishing last. Anything done out of order gets damaged by what follows it.

Society permissions come before all of it. Most housing societies in Indian metros require written intimation, restrict working hours, prohibit weekend work, and ask for a refundable deposit against common-area damage. Some prohibit structural and plumbing changes outright. Find out before you commit to a start date.

Set up for dust before demolition, not after. Sealing doorways with plastic, covering the flooring you are keeping, and agreeing where debris is stored and how often it leaves are worth writing into the contract. Debris left on a landing is how a renovation becomes a dispute with neighbours.

Keep a running list of decisions still open with a date against each. Renovations do not usually stall on money; they stall on a shutter finish nobody has confirmed while three trades wait.

Renovations rarely stall on money. They stall on one unconfirmed decision while three trades wait.

Build your bill of quantities

Read next

More on this.

The drawings you need before you call a contractorProcess

The drawings you need before you call a contractor

A quote against a sketch is a guess with a number attached.

Process · 6 min
Home lifts: the questions to ask before the shaft is castProcess

Home lifts: the questions to ask before the shaft is cast

Almost every regret about a home lift is a decision made after the structure was poured.

Process · 7 min
Switches and sockets: count them before the walls closeProcess

Switches and sockets: count them before the walls close

Nobody has ever finished a house wishing they had fewer sockets.

Process · 6 min